Meaning
Development phase focused on narrowing down technical options and defining the project scope more clearly. Work during fel-2 transforms the initial business idea into a specific engineering concept. This stage concludes when a single preferred option is selected for detailed design.
Technical Alternative
Different engineering solution considered to solve the primary business problem. During fel-2 the team compares various technologies and layouts to determine which offers the best return on investment. Each option is evaluated based on its cost and the operational risks it introduces to the facility.
Facility Selection
Determination of the exact location and physical configuration of the proposed assets. The output of fel-2 includes a plot plan and a list of utility requirements for the chosen site. Defining these physical boundaries early prevents expensive changes later in the engineering cycle when the cost of modifications is much higher.
The team also investigates environmental impact and soil stability to ensure the ground can support the weight of the new structures. A failure to identify these physical constraints now can lead to massive cost overruns during the piling and foundation work of the build phase. This level of detail provides the certainty needed to move toward a firm budget and schedule.
Scope Boundary
Definitive list of what is included in the project and what remains outside of it. A clear description of the work during fel-2 prevents scope creep by establishing a firm baseline for the next stage of engineering. This document lists the battery limits and the specific systems that the contractor must deliver to the owner.