Meaning
Priority sequencing rules that determine the order of job execution on a factory floor by dividing the time remaining until a job’s due date by the work time still required. Applying critical ratio dispatch allows production schedulers to dynamically adjust task order based on real-time urgency. It balances job progress against strict delivery commitments.
Mathematical Calculation
Schedulers calculate a ratio where a value of less than one indicates a job is behind schedule, while a value greater than one means a job has slack time. The formula uses current calendar date, promised delivery date, and remaining processing hours. It updates continuously as new shop-floor data arrives.
Priority Resolution
Jobs with the lowest ratio receive the highest processing priority at each work center. This allocation focuses resources on items most likely to incur late penalties. Schedulers rely on this sequence to prevent delays across complex multi-step routings.
Operational Limit
Effectiveness decreases when raw material arrivals are highly unpredictable or when bottleneck stages are overloaded. The method assumes that job files contain accurate processing times and that machines do not experience unscheduled breakdowns. If these assumptions fail, the calculated priorities can lead to excessive setup changes and reduced overall machine utilization.